THE ENFIELD EIGHT

Enfield, LONDON.

November 2017.

MATERIALS

Various Mild Steel Sections

Composite Deck Flooring

 

FINISH

Galvanised & Powder-Coated

Traffic White - RAL9016

TRAVEL DISTANCE

218 Miles/4h 4mins

INSTALLATION TIME

Removal, excavation,

concrete pour, install.

11 Days

Out with the old and in with the new..8 times!

We were contracted by a Residential Housing Committee to remove and replace the existing Balconies on a Block of residential flats in Enfield, North London. The whole project was to include the removal and disposal of existing 2-Tier Balcony Structures, the upheaval of patios below, break & remove the original concrete pads, excavate the 7 x holes to 1m x 1m x 1m, pour a cubic metre of concrete per hole and the, one-by-one, install the new, White Ironwork Balconies. Removing the old Timber structures was the easiest aspect as they were so rotten in places that some literally fell down. The finishing touches of this project included the replacement of the patio flags which were eventually sourced from a local 'Selco'.

The entire project took 3 x weeks to manufacture, galvanise & powder coat and 10 working days (plus a Saturday morning) to complete the removal & install. Not to mention.. 7 Tons of earth, rubble, timber & concrete removal, 5 x skips, 5 tons of new, barrowed concrete and countless cups of coffee!

If you have a similar project that you would like us to undertake.. Don't hesitate to get in touch.

 

A family concern since 2001. Trust the experts!

CSW Fabrications,

Unit 24, New Hall Hey Business Park,

Rossendale,

Lancashire,

BB4 6HL.

Popular Pages

 

About

Our Products

Past Projects

Reviews

Social

Blog

 

  • Facebook
  • Instagram

Copyright 2019 CSW FABRICATIONS. All photos & editorial are the intellectual property of CSW FABRICATIONS.. So please don't 'steel' them.